Narbethong Special School, Buranda

Back
Narbethong Special School, Buranda Thick blue line

Type:

Hydrotherapy pools

Project:

Construction of heated student learning pool

Completion:

July 2010

Pool:

Surface area: 53 sq.metres
Volume: 45,300 litres

Water Treatement System:

Filtration: 2 no. Poolrite S9000 sand filters
Pumps:2 no. Sta Rite 3E pumps
Sanitation: 2 no. Autochlor AC50RP salt chlorinators
PH Control: AcidORP & PH
Monitoring: Aquarius
Dosing: Alldos
Heating: Raypak 280 commercial

Pool Finish:

Coping: Exfotliated granite
Interior surface: Fully tiled Metz Klinkasire
Handrails: Custom stainless steel

Baldwin Aquatic worked collaboratively on the production of this learning pool, which is raised to 5m above ground level.

As part of the ‘Building the Education Revolution’ (BER) program, the Narbethong Special School was granted permission for the construction of a heated pool. Baldwin Aquatic was engaged by the main contractor, Broad Constructions, to provide a design and construct package for the 11m x 5m training pool.

Due to the school’s location in a flood area, the pool had to be raised 5m above ground level, to what is effectively the second story of the school building. The pool is heated and fully tiled in Metz KlinkerSire tiles.