Construction resort lagoon pool
July 2007
Surface area: 1415 square metres
Volume: 1,404,000 litres
Filtration: 3 no. Waterco M3750 sand filters
Pumps:3 no. Aquaplus 125-20 7.5kw pumps
Sanitation: Salt Autochlor AC-1000
PH Control: AcidORP & PH
Monitoring: Aquarius SE100WP
Dosing: Alldos
Coping: Exfotliated granite
Waterline: Bisazza
Interior surface: 1-2mm quartz pebble
In July 2006, Baldwin Aquatic won the tender to construct swimming pools for the Peppers-managed Blue on Blue Resort, located on Magnetic Island.
The first stage, completed in December 2006, included an 18m x 12m lagoon pool, as well as 7 luxury plunge pools for the waterfront villas. Second stage construction began in March 2007 and included an 90m long/1300 sq m lagoon pool, as well as 8 luxury plunge pools. The pools feature exfoliated granite coping and Italian Bisazza waterline tiles. Interiors, finished with 1mm white pebble featuring a dash of black, complement the stunning blue-green hues of the tropical waters.